ESTIMATE OF A RCC BOX, SPAN 6 M, CLEAR HEIGHT 6.0M, FORMATION HEIGHT ABOVE BED 8 M
RCC box is a highly populated small span bridge being constructed in Indian Railway and in many road bridges also. Most of the RCC box in Indian Railway is provided with single opening. There are few bridges with 02 openings may be 10% of the minor Boxes. Multi span boxes having 03 or more openings are banned now.
RESTRICTION IN THE USE OF RCC BOX ON INDIAN RAILWAY PERSPECTIVE.
1. RCC Box type minor bridges are opted using as balancing culvert in Indian Railway.
2. It is a minor bridge with Shallow foundation. Depth of M15 leveling course is only 1.35m from bed level.
3. In flowing Stream/ Nalliah, bed is subjected to scour, hence RCC box bridge can not be opted, even in occasional flow where scour is apprehended.
4. RCC box is placed on top soil generally with a poor bearing capacity. Required bearing capacity as suggested by the designer has to be ensured by excavating the top soil, 500mm to 1000mm even more, below the levelling course and filled with sand in layers and consolidated.
5. Being Top soil, a poor bearing capacity, subjected to settlement/unequal settlement, chances of failure is more than usual in multiple boxes.
As per Railway standard and RDSO DRAWING an estimated cost of a RCC box bridge is tabulated below.
DETAILS OF GIVEN DATA/ DESIGNED DATA
1. Opening 6m x 6.15m (Inner height)
2. Top Slab, Bottom Slab and Vertical wall thickness: 700mm
3. Haunch: 0.6m x 0.6m
4. Height of Bank above Bed= 8m
5. Formation width of single track=7.85m
6. Boulder Backing thickness = 0.6m
7. Curtain Wall/Drop Wall thickness = 0.3m
8. Wing wall thickness at top= 0.30m
9. Wing wall thickness at bottom= 0.80m
10. Base footing of Wing wall, thickness: 0.8m
11. Base footing of Wing wall, wide: 6.9m.
12. Barrel Length of the Box: 13m
13. Sand filling below Box/Wing wall base 0.5m
14. Schedule of Rates followed DSR'21, IRSSOR'2019
Based on the data mentioned above Estimated quantity and costing of a typical RCC box is tabulated below.
Considering a RCC column/beam structure, steel is provided fo
1. Footing, 2. Plinth Beam, 3. Lintel (continuous ), 4. Beam, 5. Slab, 6. Column. 7. Stair case. and other features like septic tank etc not considered.
Considering height of the building= 3.34m
ntity of Steel required for
1. Slab= 650 kg
2. Footing=340 Kg
3. Column=650 kg
4. Plinth Beam=520 kg
5. Continuous Lintel= 400 kg
6. Beam= 760 kg
7. Stair case=65 kg
8. Stair case Roof=60Kg
Total=3445 kg i/c wastage 5%.
A. M20 CONCRETE- MATERIAL REQUIREMENT 10' X 10' X 5'' THK.=41.5 CFT=1.18CUM.
1. Given Data:
2. Wet Volume of concrete =10' x 10' x 0.4166'(5'') =41.7 cft.=1.18cum.
3. Increasing 54%, dry volume of the concrete=1.18 x 1.54=1.82cum.
4. Quantity Calculation:
a. Quantity of Cement = Dry volume x (a/{a+b+c})
=1.82 x (1/{1+1.5+3}.
= 1.82 x (1/5.5}) = 0.331cum= 0.331 x 1440= 476.5 kg =9.53 bags approx.
b. Quantity of sand = Dry volume x (b/{a+b+c}
∴ Quantity of sand = Dry volume x (1.5/5.5)
= 1.82 x (1.5/5.5}) = 0.496 cu.m=0.496 x 35.31= 17.5 cft approx.
c. Quantity of Stone Aggregate:
= 0.9927 cum= 0.9927 x 35.31= 35 cft approx.
B.MATERIAL REQUIREMENTS OF CEMENT MORTAR IN BRICK WORK (1:6)
1. Given Data:
a. Quantity of Brick Work= 5 cum
b. Ratio of Cement Sand Mortar=1:6
c. Mortar thickness generally =10mm.
d. Size of Bricks(modular)= 190 x 90 x 90 mm.
e. Bulk density of Cement= 1440 Kg/cum.
2. Size of Brick with Mortar= 200 x 100x 100mm.
3. Volume of one brick including mortar=0.2 x 0.1 x 0.1=0.002cum.
=5 / 0.002=2500nos.
5. Total volume of bricks only=2500 x 0.19 x 0.09 x 0.09=3.8475cum.
6. Wet Volume of Mortar= Volume of Brick work - Volume of 2500nos. of bricks.=5 - 3.8475=1.1525 cum.
7. Increasing 15% for frog filling, wastage etc, wet volume comes as=1.15 x 1.1525 = 1.3254cum.
8. Increasing 33%, Dry Volume of Mortar will be= 1.33 x 1.3254 = 1.7627 cum.
9. Quantity Calculation-cement
a. Cement
b. Ratio of Cement Sand Mortar-1:6
c. Sum of the Ratio of Cement and Sand=1+6=7
d. Quantity of Cement=(Vol. of Dry Mortar x Ratio of cement)/Sum of the Ratio=(1.7627 x 1)/7=0.252cum.
= 1440 x 0.252=363kg.=7.26bags
10. Quantity Calculation-Sand
a. Quantity of Sand= (Volume of Dry Mortar x Ratio of sand) / Sum of the Ratio=(1.7627 x 6)/7=1.511cum.
=1.511 x 35.31=53.35cft.
B.MATERIAL REQUIREMENTS OF CEMENT MORTAR IN BRICK WORK (1:4)
1. Given Data:
a. Quantity of Brick Work= 5 cum
b. Ratio of Cement Sand Mortar=1:4
c. Mortar thickness generally =10mm.
d. Size of Bricks(modular)= 190 x 90 x 90 mm.
e. Bulk density of Cement= 1440 Kg/cum.
2. Size of Brick with Mortar= 200 x 100x 100mm.
3. Volume of one brick including mortar=0.2 x 0.1 x 0.1=0.002cum.
4. No. of bricks with mortar alround=Volume of Brick work(5 cum)/Volume of one brick with mortar
=5 / 0.002=2500nos.
5. Total volume of bricks only=2500 x 0.19 x 0.09 x 0.09=3.8475cum.
6. Wet Volume of Mortar= Volume of Brick work - Volume of 2500nos. of bricks.=5 - 3.8475=1.1525 cum.
7. Increasing 15% for frog filling, w
astage etc, wet volume comes as=1.15 x 1.1525 = 1.3254cum.
8. Increasing 33%, Dry Volume of Mortar will be= 1.33 x 1.3254 = 1.7627 cum.
9. Quantity Calculation-cement
a. Cement
b. Ratio of Cement Sand Mortar-1:4
c. Sum of the Ratio of Cement and Sand=1+4=5
d. Quantity of Cement=(Vol. of Dry Mortar x Ratio of cement)/Sum of the Ratio=(1.7627 x 1)/5=0.3525cum.
= 1440 x 0.3525=508kg.=10 bags nearly.
10. Quantity Calculation-Sand
a. Quantity of Sand=
(Volume of Dry Mortar x Ratio of sand) / Sum of the Ratio=
(1.7627 x 4)/5=1.411cum.
=1.511 x 35.31=49.8 cft.
C. MATERIAL REQUIREMENTS OF CEMENT-SAND PLASTER IN BRICK WALL.
1. Given Data:
a. Quantity of plaster-100m2
b. Ratio of Cement Sand-1:6
c. Plaster thickness=12mm.
d. Bulk density of Cement- 1440 kg/cum.
e. Weight of cement bags- 50 kg
2. Volume of plaster= 100m2 x 0.012=1.2cum.
3. Adding 20% for filling unevenness, joints etc wet volume of mortar comes to-1.2 x 1.2=1.44cum.
Dry volume of mortar(increasing 33%)=1.44 X 1.33=1.92 cum.
4. Quantity Calculation:
a. Sum of the Ratio of Cement and Sand= 1 +6 =7
b. Quantity of Cement=(Volume of Dry Mortar x Ratio of cement)/ Sum of the Ratio =(1.92 x 1)/7=0.2736 cum
c. Quantity of Cement in Kg.=0.2736 x 1440=394kg.
d. Quantity of Cement in bags=394/50=7.88 bags
e. Quantity of Sand= (Volume of Dry Mortar x Ratio of sand) / Sum of the Ratio =(1.92 x 6)/7=1.6416 cum.= 1.6416 x 35.31=58 cft.
D. REQUIREMENTS OF BRICKS IN 100 SFT WALL, 9''THK.
1. Given Data:
a. Size of wall 10' x 10' x 9'' thk.
b. Size of one brick 9''x 4.5'' x 3''
c. Thickness of mortar= 10mm=10/25.4=0.393''
2. Area of wall face=
10' x10'=100sft.=100x12x12=14400 sq inch.
3. Due to mortar 02 sides i.e 4.5'' and 3'' each will be increased by 10mm or 0.3937inch.
4. Size of exposed face with mortar of a brick will be=4.8937'' x 3.3937''
5. face area representing one brick with mortar=4.8937'' x 3.3937'' =16.61sq.inch.
6. No. of bricks= Total face area of wall/exposed face area of one brick with mortar.
=Sl no.2 / Sl no.5=14400/16.61=867nos.
E. REQUIREMENTS OF BRICKS IN 100 SFT WALL, 4''THK.
1. Given Data:
a. Size of wall 10' x 10' x 4'' thk.
b. Size of one brick 9''x 4''x 3''
c. Thickness of mortar= 10mm=10/25.4=0.393''
2. Area of wall face=
10' x10'=100sft.=100x12x12=14400 sq inch.
3. Due to mortar 02 sides i.e 9'' and 3'' each side will be increased by 10mm or by 0.3937inch.
4. Size of exposed face with mortar of a brick will be=9.3937'' x 3.3937''
5. face area representing one brick with mortar=9.3937'' x 3.3937'' =31.88 sq.inch.
6. No. of bricks= Total face area of wall/exposed face area of one brick with mortar. =Sl no.2 / Sl no.5=14400/31.88=452nos.
F-Estimating and costing of Rubble Stone Masonry with cement mortar 1:6:
1. Let quantity of Stone masonry=10 cum.
2. Quantity to be brought at site taking into account wastage, voids etc, extra 30%.
3. Quantity of stone boulder=1.3 x 10=13cum.
4. Volume of wet Cement mortar required=30% of 10 cum, quantity of Masonry=3.0 cum.(In brick work this is nearly 22 % of brick work)
5. Volume of Dry Cement mortar, increasing 33 %= 3 x 1.33 =4cum.
6. Quantity of cement=Dry volume x ratio of cement/sum of the ratios=4 x1/(1+6)=4/7=0.57cum.=0.57 x 1440=820kg=17bags
7. Quantity of sand=Dry volume x ratio of cement/sum of the ratios=4 x6/(1+6)=24/7=3.429 cum.=3.429 x 35.31=121 cft.
Costing: materials cost shall be taken from local market. However effort is given to have a rough costing in kolkata area.
1. Rubble stone 13Cum @
2. Cement 17 bags @ Rs375/- per bag=6460/-
3. Sand 121 cft @ 47/- =5687/-
4. Add L/S cost 2 % for water, electricity
5. Add labour Cost @ 15%, considering material available within a lead of 10m and lift up to 3.5m
6. Add contractors profit @ 12.5%.
G. How much does 1,000 sq ft slab work cost?
Assuming residential house up to 02 story:
1. Area of the slab in m2=93 sqm.
2. Thickness of Slab assumed=125mm
3. Volume of weight concrete for slab= 93 x 0.125=11.625 cum.
4. Volume of concrete for beam projection 32% of Slab quantity=
0.32 x 11.625=3.6cum.
5. Total volume of concrete= 11.625 + 3.6=15.225 Cum.
6. Dry volume of concrete= 1.53 x 15.225=23.3 cum
7. Assuming 1: 1.5: 3 concrete,
a. Volume of cement=4.24 cum=122 bags.
b. Volume of sand= 6.36 cum.=225 cft
c. Volume of Stone chips=12.72cum=450 cft.
8. Reinforcement
a. Slab Reinforcement 62 Kg per 100 sqft= (62/100) x 1000=620 Kg.
b. Beam reinforcement: 76 Kg per 100 sft=(76/100) x 1000=760 Kg.
c. Total Steel = 620 + 720= 1380 Kg.
9. Costing:
1. Cement: 122 bags x 375/-=45750/-
2. Sand: @47/- per cft for 225 cft x 47=10,575/-
3. Stone chips: @ 58/- per_ cft., for 450 cft cost comes to:26100/-
4. Reinforcement 1380 kg x 68/- = 93840/-
5. Labour/mason cost for casting i/c ply wood shuttering, bamboo props, excluding vibrator etc: @ 70/- per sq ft=1000/-x 70/-=70000/-
6. Hire charges of vibrator @ 1200/- per day
Total cost for 1000 sqft slab including Beam
=45750/- + 10,575/- + 26100/- + 93840/- + 70000/- + 1200/- = Rs.2,47,465/-
Hence Cost per Cum of Concrete= 2,47,465/- / 15.25= Rs16227/-
Add 2% for wastage and miscellaneous cost.
H. REQUIREMENTS OF BRICKS IN 100 SFT WALL, 10"THK.
1. Given Data:
a. Size of wall 10' x 10' x 10'' thk.
b. Size of one brick 9.75''x 4.75'' x 2.75'' (In west Bengal, this size is adopted in general)
c. Thickness of mortar= 10mm=10/25.4=0.393''
2. Area of wall face=
10' x10'=100sft.=100x12x12=14400 sq inch.
3. Due to mortar 02 sides i.e 4.75'' and 2.75'' each will be increased by 10mm or 0.3937inch.
4. Size of exposed face with mortar of a brick will be=5.1437'' x 3.1437''
5. face area representing one brick with mortar=5.1437'' x 3.1437'' =16.17 sq.inch.
6. No. of bricks= Total face area of wall/exposed face area of one brick with mortar.
=Sl no.2 / Sl no.5=14400/16.17=890nos.
7. No. of Bricks per cum of above brick wall
Total Volume=100sft. x 0.833=83.3 cft.=2.36 cum.
Therefore 2.36 cum brick work contains- 891 bricks
Bricks required per cum= 891/2.36=377 nos.
J. BAR BENDING FOR STIRRUPS FOR BEAM AND COLUMNS
Cutting Length of Rectangular Stirrups:
7. Deduction for 90 deg bend=2d, d= dia of footing bar = 2 x 12= 24mm
Cement required for 10 sqm area of floor
1. 20mm thk cement mortar
a. Volume of wet mortar=10 x 0.02=0.2 cum.
b. Volume of dry mortar=1.33 x 0.2=0.266cum.
c. Sum of the ratio=4+1=5
c. Volume of cement=0.266/5=0.0532cum=77kg.
2. Grey cement slurry @ 44 kg/10sqm=44 kg
3.White cement for filling joint@ 44kg per 10 Sqm=44kg.
Total Cement=77 + 44 + 44=165 kg for 10 sqm.
COST OF TRACK MATERIAL
Date: 11.09.21
A: COST OF 1 KM TRACK MATERIAL STRAIGHT TRACK |
|||||||
Description of Item |
Unit |
qty |
Basic cost of Material |
Transp, inspecn and overhead 26% on C-4 |
GST-18% on C-5 +C-4 |
Unit rate |
Amount |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
Supply of 52 kg rail 90 uts |
MT |
105 |
62500 |
16250 |
14175 |
92925 |
9757125 |
Supply of PSC sleeper BG Mono Block |
No. |
1540 |
1920 |
499.2 |
89.9 |
2830 |
4357553 |
Supply of elastic Rail Clips |
No. |
5544 |
60 |
15.6 |
2.8 |
87 |
484087 |
Supply of grooved rubber sole plate |
No. |
3080 |
30 |
7.8 |
1.4 |
44 |
134378 |
Supply of Metal liner |
No. |
5544 |
50 |
13 |
2.3 |
68 |
376257 |
Supply of fish plate |
Set |
154 |
2460 |
639.6 |
115 |
3636 |
559907 |
Supply of fish bolts and nuts +
washer=55.51 |
No. |
616 |
50 |
13 |
2.3 |
75 |
45985 |
Supply of end cut liner |
No. |
616 |
20 |
5.2 |
0.9 |
32 |
19574 |
Supply of J type clips |
No. |
616 |
55 |
14.3 |
2.6 |
78 |
48161 |
Total Cost of 1 KM Track materials= |
|
|
15783026 |
||||
Cost per M track= |
|
|
|
|
|
15783 |
0 Comments